Floods wreck havoc in Kampala

BY: Eyalama In Business, News On

Traffic and business came to a standstill today Wednesday following a heavy downpour in Kampala.

The most affected roads were John Babiiha road where road construction works are on-going and Kyaggwe road near Swaminarayan Temple. People with businesses along Kyaggwe road were forced to close after water entered their shops.

Business at Ham Shopping Grounds also came to a standstill as Nakivubo Channel overflowed and left the shops submerged in water. The floods flowing from Clock Tower to Nakivubo Channel submerged the road making it nearly impassable for pedestrians and small cars. Some people were forced to remove their shoes, fold their trousers and wade through the floodwaters.

Some men were seen charging Shs 1,000 to carry pedestrians who didn’t want to wade through the water, on their backs. This isn’t the first time Clock Tower is flooding. Various attempts have been made in vain to improve the drainage and ease the water flow.

Uganda

Confirmed
75,537
Deaths
781
Recovered
50,350
Active
24,406
Last updated: June 25, 2021 - 4:29 am (+00:00)
Flooding on Kyaggwe road

Brian Bagala, an engineer in charge of drainage at Kampala Capital City Authority (KCCA) says the Clock Tower is bound to flood especially now that the area is excavated as works continue under the Kampala flyover project. He says as works proceed, some of the drainages in the area has been affected.

He, however, says the status will improve when the flyover project is concluded and the drainage in the area is worked upon. The Nakibubo Channel is the converging area for storm-water in the central business area.

Kenya

Confirmed
181,239
Deaths
3,538
Recovered
123,462
Active
54,239
Last updated: June 25, 2021 - 4:29 am (+00:00)

Over 500 manholes are placed in the city leading storm-water into Nakivubo Channel. However, the channel is overwhelmed due to the grounding erection of buildings that have taken up the green spaces that could accommodate water.

Nakivubo channel

In 2019, with funding from World Bank under the Kampala Institutional Infrastructure Development Project, KCCA contracted a consultant company, Nippon Engineering to study the channel and conduct an assessment, modelling and redesigning of the catchment area.

Rwanda

Confirmed
34,143
Deaths
402
Recovered
26,865
Active
6,876
Last updated: June 25, 2021 - 4:29 am (+00:00)

The consultant was supposed to conclude works by this month but Bagala says their activities were interrupted by COVID-19 lockdown and were hence granted more time until December 2020.

Add your comments:

Download Our News App Here

You may also read!

Gen. Wilson Mbadi appointed new Chief of Defence Forces ( CDF )

President Museveni has promoted Wilson Mbasu Mbadi to the rank of General and appointed him as the new Chief of

Read More...

I will advise Museveni to prepare for a smooth transition of power-Gen. Elly Tumwine

Outgoing Security Minister Gen. Elly Tumwine who was appointed as a Senior Presidential advisor on security has pledged to

Read More...

Covid-19 vaccination exercise to resume next week

A total of 175,200 AstraZeneca vaccines will be administered to people who received their first jab 12 weeks ago

Read More...

Comments are closed.

Mobile Sliding Menu